Timeline: It takes 4-6 weeks weather permitting after permits are obtained.
1st Stage 2nd Stage 3rd Stage 4th Stage 5th Stage 6th Stage 7th Stage 8th Stage 9th Stage
Excavation 8 hours
Steel and Plumbing one day each
Gunite One day installation and then cutting for several days
Tile and Coping 2-3 days
Install Decking Forms One day to set
Clean and Grade of Land

Sprinkler Reroute

2-3 days
Plaster Installation

and fill with water

1 day
Landscaping and Fence Repair or Installation 2-3 days
Pool is full of water Customer receives pool school and pool is started!